Kincardine okays sewage pumping station upgrades despite high price tag

Liz DadsonBy: Liz Dadson  November 14, 2021
Kincardine okays sewage pumping station upgrades despite high price tag
Kincardine council has awarded the tender for the Huron Terrace sewage pumping station upgrades, even though the one and only bid was substantially higher than the amount budgeted.

In committee-of-the-whole Monday night (Nov. 8), Adam Weishar, director of infrastructure and development, put forward the recommendation that council award the tender to Finnbilt General Contracting Limited of Stratford, in the amount of $4.23-million - the budget was $3-million.

He said the project will actually be almost $2.3-million over-budget, given the other items already purchased, including $138,605 for engineering and $654,062 for pre-selected equipment, leaving only $2.2-million in the budget.

Weishar said this project is one component of the Huron Terrace Pumping Station catchment area upgrades, with work currently under way and nearing completion on the forcemain replacement.

This sewage pumping station is the main one in the Kincardine Wastewater System, said Weishar. All sewage from the Huron Terrace, Connaught and Durham collection systems is routed through this pump station. With pending development, such as West Ridge on the Lake, the current station requires upgrades to ensure sufficient capacity is available for the increased flow of sewage.

Weishar noted that the single tender submission is substantially higher, and that several factors contributed to the total tender price for this contract:
 
  • The initial scope of this work did not include some sewer and maintenance installation upstream of the sewage pumping station, access road and parking improvements. These necessary additions to the scope have a total value of $320,000.
  • The initial budget for the temporary bypass pumping equipment, required to maintain sewage flows, was $113,000; this budget reflected an assumed staging of the new works and temporary powering and connection of the new equipment while completing the project in its entirety. However, due to the increased cost of material and the labour required to perform the work, the presented bid is nearly $340,000.
  • Due to the impact COVID-19 has had on the supply chain, the cost of materials continues to increase. Specific to this project, the cost of metals, piping and electrical components has been most significantly affected and continues to increase. The cost for the Huron Terrace Sewage Pumping Station motor control centre is $530,000, compared to the 2017 Connaught Station budget of $190,000.

Finnbilt has been deemed compliant and credible by the municipality’s engineer, B.M. Ross and Associates, said Weishar, and staff agree the tender submitted meets the requirements of the upgrades.

The contractor has indicated the work will take 60 weeks, and Weishar said that given this length of time, and the need to increase capacity to support developments under way and others pending, staff is recommending council award the tender to Finnbilt.

The project is to be funded from the sewer reserve fund, which currently has sufficient funds to support the additional costs.

“I’m not pleased with this at all,” said councillor Dave Cuyler. “Things happen and there is a lot of this that’s due to COVID-19 but a lot of it isn’t. This is something we need. It’s going to cost a certain amount, but we’re passing a tender that is almost twice as much.”

Councillor Bill Stewart asked the two representatives from B.M. Ross, Andrew Garland and Dale Erb, who were attending the Zoom meeting, to explain what happened.

“We sympathize with you,” said Garland. “It has not been a fun year for taking on building projects.”

He said the trend over the past one-and-a-half to two years has been to see cost over-runs in construction, in residential as well as municipal infrastructure. He noted that a water tower bid came in almost 50-per-cent over-budget.

“This is an early tender call, with construction in 2022,” said Garland. “I was surprised there was only one bidder when there are three to four contractors that do this work. It’s a volatile market; it’s an unfortunate reality.”

“It’s unfortunate for the taxpayers who are paying the price,” said Stewart. “What about your consulting fee?”

“The budget is based on the hours that go into the project,” said Garland. “It did not include the increase in materials.”

Weishar said the capital projects are based on a water and wastewater master plan done in 2017. The Huron Terrace sewage pumping station upgrades were slated for engineering in 2020 and to tender and construction in 2021. However, the COVID-19 pandemic shelved the project for six to eight months.

“We have moved it along as fast as possible,” said Weishar.

Garland said the master plan called for upgrading the pumping station capacity due to aging infrastructure and the growth in the municipality.

“I’m confused,” said councillor Laura Haight. “Is there a suggestion that this next phase was unknown? I was water and sewer chair when this began. It was brought forward in October/November of 2016 when we realized the need for increased sewage capacity for the West Ridge on the Lake development and as the community grew to the north. This has been going on for 10 years, based on growth.

“I am disappointed with the numbers, yes, but it’s a weird time.”

Stewart suggested putting the $2.3-million that the project is over-budget, into the 2022 budget. He also suggested the municipality look at another engineering consulting company.

Councillor Dorne Fitzsimmons asked what is actually needed for the pumping station upgrades?

“We’ve heard there are developments coming on-line,” he said. “We also have several developments approved but they’re just sitting there.”

Weishar said the Huron Terrace pumping station is the collector point for Connaught Park and Durham Street, which includes all the property north of the Sutton Park Inn, as well as the Kincardine hospital and West Ridge on the Lake.

“We won’t be able to support that West Ridge on the Lake phased development,” he said. “We can’t crystal-ball when the projects are coming to fruition. But we don’t want to be in a position where developers can’t go ahead (due to a lack of sewage capacity) so they go elsewhere. In the five years I’ve been here, there has been a lot of interest and development in Kincardine.

“Council is in a tough spot. If you award tonight, you’re over-paying. If you wait and take the risk of re-tendering next year, you might close the door on some developers.”

Cuyler agreed. “We’re caught between a rock and hard place. I’m going to support this, but begrudgingly.”

“We’ve been hamstrung by a lack of government grants for infrastructure,” said councillor Maureen Couture. “From an economic development point of view, there are a number of people waiting to move forward with projects. We don’t want to wait till spring to re-tender, and then have to wait another year after that for construction to be complete. I’m also disappointed that we had only one bidder, and with the high price.”

Stewart asked if B.M. Ross had contacted the other companies that had taken tender packages but did not bid on the project.

“We talked to a couple of them,” said Garland. “Given the complexity of the project and all the other work they had on the go, they were unable to do it. Plus, they are struggling to find labourers.”

Committee-of-the-whole agreed with the recommendation to award the tender to Finnbilt General Contracting Limited, in the amount of $4.23-million. That was later endorsed by council.

Treasurer Roxana Baumann said if the project is over-budget, council can approve a budget amendment to increase the funding from the sewage reserve fund.

Related Stories

No related stories.

Share

    Comments (0)

  1. No Comments.

Leave a Comment

By submitting this form, I consent that my name (and email, if provided) will be published on kincardinerecord.com as part of this story.


Banner Ad
Banner Ad