Reconstruction project under way in downtown Kincardine
The reconstruction of Queen Street in downtown Kincardine has begun.
Fencing went up from Durham Market South to Harbour Street late last month, marking the first phase of the project, as water, sewer and storm-sewer lines are replaced.
At the intersection of Queen and Harbour Streets, sanitary and storm-sewer lines will connect and outlet into the Harbour Street pipes.
Phase 1 is expected to be complete by late July.
Phase 2, from Harbour Street to Lambton Street, is to start in late May, with completion by late September.
Phase 3, from Lambton Street to Durham Street, is to start in mid-July, with completion by November.
Each phase includes its own temporary watermain, and restoration of each phase will follow after underground work is completed. The majority of construction is set for completion in November, while streetscaping (trees, planters, furniture, etc.) and the topcoat of pavement are to be completed in 2024.
Project scope and objectives:
- Replacement of storm sewers, sanitary sewers, watermains, and services
- Improved accessibility for sidewalks and building entrances
- Flexible landscaping including movable planters
- New accessible ramp and entrance for the library
- Cohesive design with the lakeshore, Harbour Street, and Queen Street North.
- Full road reconstruction with new vehicular-traffic calming measures to enhance pedestrian safety
For more information, visit:
www.kincardine.ca/en/build-invest-grow/downtown-dig.aspx