Kincardine selects Queen Street Bridge over Concession 5 bridge for grant bid

Liz DadsonBy: Liz Dadson  April 16, 2019
Kincardine selects Queen Street Bridge over Concession 5 bridge for grant bid
It was a close vote, but Kincardine council has decided to submit a grant application for reconstruction of the Queen Street Bridge, located just south of the Kincardine Arts Centre in downtown Kincardine, rather than the one-lane bridge on Concession 5, east of Highway 21.

In committee-of-the-whole Monday night (April 15), council discussed the two projects, and Queen Street got the nod by a 5-4 vote.

However, contrary to discussion at the April 8 meeting, council was not as gung-ho to close the Concession 5 bridge, known as Browns Hill Bridge, after receiving numerous phone calls and E-mails, following last week's meeting.

April 8, treasurer Roxana Baumann presented several options for grant funding. Among them, was infrastructure funding for rural and northern communities, up to $5-million, with the federal government covering 50 per cent of the cost, the province picking up 33.33 per cent of the cost, and the municipality covering the rest.

Baumann brought forward both the Browns Hill Bridge and the Queen Street Bridge as options for this funding.

Browns Hill requires structure replacement and major road reconstruction to the tune of $3-million, she said. Otherwise, it will require load postings and/or closure in the future. The bridge is located on Concession 5, between Sideroads 10 and 15N.

Meanwhile, the Queen Street Bridge requires structural rehabilitation and patch repairs, to the tune of $1.6-million. However, if it's not fixed up in one to three years, it will require replacement within five to 10 years, at an estimated cost of $3-million.

Councillor Randy Roppel said there is one farm on the west of Browns Hill Bridge, and one farm at the east end. “I'd like to see this road closed. People using the landfill can just go to the next concession and go around. There are better ways to spend $3-million.”

Councillor Laura Haight said council should get a staff report before just closing the road.

Chief administrative officer Sharon Chambers said whether council wants to look at replacing that bridge or not replacing it, the municipality should still have an Environmental Assessment (EA) done.

Mayor Anne Eadie said most people from the Town of Kincardine, who use the landfill site, travel out Highway 9 and then north on Sideroad 15N. And those at the north end could use Concession 7.

Haight said council should also consult with the public before opting to close the road. “It's not just people travelling to the landfill who use it. We should defer until we get a staff report and do some consultation.”

Council agreed.



The one-lane Browns Hill Bridge on Concession 5, Kincardine, looking east

And that report came to council Monday night (April 15).

Public works director Adam Weishar told council that the staff recommendation is to apply for a grant under the "Investing in Canada Infrastructure Program (ICIP)" for Browns Hill Bridge.

“The municipality has been unsuccessful with past funding applications related to Browns Hill Bridge,” he said. “However, the treasurer has reported that interpretation of the application outcomes show a direct tie to the strong local economy and are not necessarily related to the scope of the project previously presented.”

He said as a result of past grant applications, the municipality initiated an EA which has remained stagnant since 2014. “The EA was to consider alternatives to replacement. To date, the municipality has invested $72,633 in engineering costs relating to EA work for this structure."

Weishar said that since closure and removal of the bridge was not contemplated during the EA correspondence, it would have to be recirculated and a public meeting held, allowing residents an opportunity to provide input. The cost to finalize the EA for consideration of road closure would be about $10,000-$12,000, he said.

He also noted that if council removes the bridge, that would be an alteration of a structure having heritage value and would trigger a “Schedule B” EA.

“Beyond impact to locals, removing the bridge would impact emergency services, the farming community and our own operations, directly impacting response times, the overall level of service and costs of operation,” said Weishar. “From Bruce County Road 15 to Highway 9, Concessions 5 and 7 are the only two east-west roads that access Bruce County Road 23.”

He added that if the bridge is eliminated, that would put more traffic on the adjacent sideroads which were not built to withstand high traffic volumes. “As for travel to the landfill site, asking people to use Highways 9 or 21 to commute with trailers at reduced speeds, is unrealistic and imposes a traffic safety issue on those provincial highways. Concession 5 is best suited for this traffic.”



Browns Hill Bridge on Concession 5 looking west

Weishar called for a master plan review of the 83 structures under the Ontario Structure Inspection Manual (OSIM) criteria. Of those, nine are within the Town of Kincardine, and 74 are in a rural to semi-urban environment.

As for the Queen Street Bridge, Weishar presented this as a secondary option for the grant funding. “This structure is vital to the Town of Kincardine and how traffic patterns function. Council can elect to consider a rehabilitation to extend the current service life, estimated at 25-30 years, or do nothing, leading to replacement in the next five to 10 years.”

A letter to council, from Jolene Shelton, noted that she has been a resident of the 5th Concession for the past 40 years, and uses the Browns Hill Bridge at least once per day if not more, to get to work and take her children to activities.

Not only do locals use the bridge, but so does the Kincardine community to access the Armow landfill on a daily basis, she said.

Plus, Concession 5 is home to many businesses that have employees and customers who require easy access to their business operations. These include:
 
  • Donegan's Haulage
  • C&M Construction
  • MKD Concrete
  • Clear-Vu Windows
  • Dennis Newman Construction
  • Janzti Carpentry
  • Farmers – dairy, beef, agriculture, plus milk trucks need access to the farms
  • Amish families that sell produce and meat
  • Armow Wind

“As a long-term resident of this town, a business owner and taxpayer, I have high expectations that mine and my family's contributions to the Municipality of Kincardine go toward maintaining the roads we use every day,” said Shelton.

“I'm glad we're not talking about closing that bridge tonight,” said deputy mayor Marie Wilson. “I have received phone calls and E-mails about this – it's an important issue for businesses and residents. We should make no decision until we have public input.” She added that the grant application deadline is May 14.

Councillor Dave Cuyler suggested the priority is the Queen Street Bridge, and leave Browns Hill for a couple of more years.

Other councillors urged going after the more expensive project, Browns Hill at $3-million, with the federal and provincial funding, which was also Weishar's recommendation.

“I'm nervous because it's been turned down twice,” said Eadie. “We should fix up the Queen Street Bridge and then we'll get 25-30 more years on a well-used bridge.”

A motion to submit the Browns Hill Bridge for funding, failed by a 4-4 vote. Committee-of-the-whole then approved the recommendation to submit the Queen Street Bridge project for funding.

That was later endorsed by council.



Concession 5 bridge looking east



Top of the hill before coming to the Concession 5 bridge looking west

Related Stories

No related stories.

Share

    Comments (0)

  1. No Comments.

Leave a Comment

By submitting this form, I consent that my name (and email, if provided) will be published on kincardinerecord.com as part of this story.


Banner Ad
Banner Ad